Downtown Almonte Construction Update – June 23, 2023
The Downtown Almonte Revitalization Project is entering its final stages. Please see below for the latest construction update, as of June 29, 2023.
Phase E – Little Bridge Street
Cavanagh Construction has completed the installation of the new sewer and watermain within Phase E – Little Bridge Street of the downtown core reconstruction project. Concrete wall repairs have been completed along Little Bridge Street, allowing for concrete sidewalk installations to begin in the upcoming week.
Once concrete work has been completed, road crews will begin grading work in preparation for asphalt paving. This work is on schedule to be completed before end of July 2023.
Phase F – Mill Street (upper section)
Cavanagh Construction has completed concrete work on the upper section of Mill Street between Little Bridge Street and Bridge Street. The roadway has been prepared for placement of asphalt.
Asphalt is scheduled to be completed on Friday, June 30, 2023. Mill Street will once again be open to traffic once this work has been completed.
Residents and businesses with inquiries can contact Hilary Lalonde, Project Manager, at 613-298-8524 (cell), HLalonde@thomascavanagh.ca.
After hours, please contact:
-
Tim Rainville, Sewer & Water Superintendent – 613-282-5018 (cell)
-
Randy Kubusheskie, Roads Superintendent – 613-913-9252 (cell)
The Municipality of Mississippi Mills would like to thank you for your patience and co-operation during this construction project.
Municipal contacts:
-
Robert Smith, Project Manager, Roads & Public Works Technologist – 613-256-2064 ext. 404, smithr@mississippimills.ca
-
Cory Smith, Director of Roads & Public Works – 613-256-2064 ext. 401, csmith@mississippimills.ca
For more information, please visit the Downtown Almonte Revitalization page on our website.